Emergency power checklist playbook

Goal

Verify an emergency system installation meets separation, source, and labeling requirements before inspection.

Inputs you must know before you start

  • System designation (emergency vs standby).
  • Source type and transfer equipment details.
  • Circuit routing and separation requirements.
  • Required labels and signage locations.

The path (in order)

  1. Confirm system designation and applicable article.
  2. Verify source and transfer equipment suitability.
  3. Check separation and protection of emergency wiring.
  4. Confirm required labeling and signage.
  5. Perform functional checks and record results.

This is

A practical checklist for emergency system compliance before inspection.

This is not

A full commissioning procedure or generator acceptance test.

Inspection-ready checklist

  • System designation documented.
  • Transfer equipment listed and labeled.
  • Emergency wiring separation verified.
  • Required signage installed.
  • Functional checks documented.

Worked example

An emergency lighting system is reviewed to confirm its separation, transfer switch labeling, and protected routing before final inspection.

Cross references

  • Primary: 700
  • Secondary: 701, 702